Community update
2 August 2019
Dear SSG Member,
As a member of our community, I believe it is important to keep you updated on any developments at Hunterston B Power Station.
As I explained in my letter of 18 March, following the core inspections and extensive modelling, the safety case providing the justification for return to service of Reactor 4 has been provided to ONR for their assessment. The ONR will, completely independently, review the case before deciding whether or not to approve for return to service. It is not possible for us to confirm with certainty how long this process will take; our top priority is that it’s completed with appropriate rigour.
Energy market rules require us to provide our most likely view of return to service dates.
To support time for the ONR assessment, we have declared 30 August 2019 for Reactor 4, a slight adjustment to the previously declared date of 5 August.
The safety case for Reactor 3 was submitted to ONR on 17 June and is undergoing rigorous review. Our target for Reactor 3 remains as 1 October.
More information regarding graphite can be found on our website.
I hope this information is useful to you as a member of the Site Stakeholder Group. Should you wish to ask any questions please feel free to ring the Station on 01294 826000 and ask for our Communications Officer, Nikki Thomson.
Colin Weir
Station Director